Question: 1
A newly formed development team experienced difficulty with accurately estimating product backlog items. As a result, the team failed to deliver all of the features in the sprint backlog for the past two iterations.
What should the team do to improve the accuracy of their estimates?
Question: 2
Midway through a sprint, the scrum master identifies that reassigning a certain task could help the team meet its sprint goals.
What should the scrum master do next?
Question: 3
A legal department representative contacts the scrum master because, while the project's budget has been maintained, it has exceeded its original contracted time and scope.
What should the scrum master do?
Question: 4
An agile practitioner wants to communicate the effect of technical debt on the project.
What should the practitioner do?
Question: 5
A member of a project's development team approaches the team lead and requests database administrator training. The team member believes that their inability to handle this work, and to rely on outside specialists, is impacting team velocity.
What should the agile team lead do?