Question: 1
A technical problem arises that will likely impact the stories planned for delivery in the current sprint.
What should the scrum master do?
Question: 2
During the review session, the product owner discovers that the user interface has a response time of 10 seconds. The non-functional requirements state that it should respond in less than two seconds. The team complains that this requirement was not communicated to them.
What should have been done to avoid this?
Question: 3
An agile team notices that the same problems continue to occur during multiple iterations. Several team members have suggestions to fix the problem.
What is the proper agile approach to handle this?
Question: 4
Early in a project, stakeholder analysis is performed; however, an organizational restructure redefines key roles.
What should the project team do?
Question: 5
A company has decided to combine two similar products consisting of multiple teams into one product. Engaged customers want to know how the company is looking at re-organizing it's teams.
What strategy should be employed to re-organize the teams?