Question: 1
During planning for the next iteration, an agile team identifies most of the story points that are expected to be delivered.
How should an agile practitioner work with the team to help identify the iteration's remaining scope?
Question: 2
When introducing agile processes to a company, a quality assurance (QA) manager resists and believes that the switch to agile will remove quality controls and documents.
How should the agile practitioner address this concern?
Question: 3
An organization highly values security. However, a team member on a project has found a way to save time and money with less robust security features.
What should the team member do?
Question: 4
Midway through at iteration, an agile team learns that a team member will be unavailable for the next two iterations.
As a high-performance team, what should the team do?
Question: 5
Senior management is frustrated at the lack of a detailed implementation plan that shows exactly when the project will end and when all requirements will be met. The team has been using a rolling wave planning approach so far on the project.
How should the agile practitioner explain to senior management the benefits of this approach?