Question: 1
A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.
What should the project manager do next?
Question: 2
A project is on its second iteration out of six. The team realizes that a key deliverable will depend on the acquisition of a new device.
What should the project manager do?
Question: 3
During a weekly project meeting a team realizes that a work package is no longer needed They decide to remove it from the project and the project manager agrees.
What should the project manager do next?
Question: 4
Who is the Key Person in the kick-off meeting?
Question: 5
One vendor is completing, just in time, a key deliverable of the project included in the critical path They send it to the project team for review The project team rejects it When evaluating the impact of this situation, it is estimated that the vendor will take another two months to correct the deliverable
What should the project manager do next?