Question: 1
A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.
What should the project manager do next?
Question: 2
What is a deliverable-oriented hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
Question: 3
A project manage, receives a complain. from a stakeholder that they have not received formal updates on key project milestones.
What should the project manager do?
Question: 4
Using the following data, what is the Schedule Performance Index (SPI)?
EV= $500 PV= $750 AC= $1000 BAC= $1200
Question: 5
While reviewing project documentation, a project manager discovers that modification were made without proper approvals. What should the project manager do next?