A project sponsor, project manager, and project facilitator are drafting a project charter. The final contents of this documentation will be presented to the project steering committee for review and approval. The following sections are currently documented:
* Project description
* Draft project timeline and schedule
* Rough milestones
* Draft project budget
* Draft resources required
* High-level risk review
Which of the following sections should be included in this document?
A project manager is reviewing documents to develop the project charter. While reviewing historical project documentation, the project manager decides to include the following in the charter:
* Project title description
* Preassigned resources
* Budget
* WBS
* Measurable project objectives
Which of the following components should be a part of the project management plan instead of
Tasks A and B have a duration of two days. Task A starts on Day 1, and Task B starts on Day 3. Tasks C and D have a duration of three days, and Task E has a duration of four days. Task C starts after Task A. Task D and E start after Task C. If Task A starts on December 15, which of the following is the anticipated start date for Task D?